Tender
of Project Management
for the Extended Project
in the pre-reserved Area
of
AMD Technologies (China)
Co. Ltd
1 Introduction of the Project
1.1 Civil Works
A new equipment plant, about 750m2, will be extended in the north of the present equipment plant. At the same time the smooth transportation of the goods passing in and out of the end product workshop should be guaranteed. The roof of the equipment plant will be used for the placement of the cooling water-tower, water tank, etc.
Other civil works relating to the project.
1.2 Internal Decoration
The present pre-reserved 3,000m2 area will be changed into production plant with the same decoration standard with the present production plant.
The decoration standard of the new equipment plant is the same as the present equipment plant.
1.3 HVAC System
The temperature requirement for the production plant is from 18℃ to 28℃, and the humidity requirement is from 35% to 65%. The contractor should design the configuration of the air-conditioning system based on these requirements and the general standard criterion to meet the ownerrsquo;s requirements.
The temperature requirement for the machine room and power distribution room is below 30℃.
The newly added technological wind-exhausting amount is about 700m3/hr.
1.4 Mechanical and Electrical Installation
Refrigeration equipment and affiliated equipment will be installed according to the requirements.
Air-conditioner and affiliated equipment will be installed according to the requirements.
Heat-transforming station of technological cooling water will be installed according to the requirements. The amount of technological cooling water being added 5,300KW.
Installing pipes from the present air-compression system to the pre-reserved area and the places where the compressed air is needed.
1.5 IT System
DDC system
IT cable tray
1.6 Fire System
The design of the fire prevention system should meet the requirements of the related national regulations and FM.
The control of the present fire prevention system and the fire prevention system of the pre-reserved area should be integrated into a centralized controlling system.
The design of the fire prevention system should be compatible with the present fire prevention system.
1.7 Electrical System
The transforming station will be enlarged with 8,000KVA.
Power distribution will be added for the power facilities.
The power distribution for the technological equipments (to the power distribution cabinet on site).
Lighting system.
The installation of other related electrical system.
All the design should meet the requirements of the related national regulations and international general standards of the related industry.
1.8 General Introduction of all the Power Facilities
4times;2000KVA air-compression equipment.
3times;450 (refrigeration quantity) refrigerator.
3times;18.7m.3/hr air-compression equipment.
2times;25,600m3/hr new wind equipment.
2 General Introduction of the Management Company
2.1 General Introduction of the Company
Genway Workshop Industry Development Co. Ltd, the registration fund is 300 million Yuan(RMB), total property is nearly 1300 million Yuan(RMB). The main business of the company includes: The development of workshop relative facilities; General contract project management of workshop; Workshop project consultant serves; Workshop industry management.
2.2 Service Tenet
Providing professional consulting, experience and management with professional thoughts. Through our professional service, our employer will gain high-efficiency and low-cost income with the project risk being reduced to the lowest level.
2.3 Service Provided
(1) At the project decision-making stage, our company participates in making the project scale and scope, and provides project planning and feasibility study and prepares feasibility study report.
(2) Assisting to finish project based design.
(3) Assisting the employer to enter into the contract with general contracting company, surveying company, designer, and supplier and supervising company of the construction project, and supervising the execution of the contract at the request of the employer.
(4) At the execution stage of the project, our company provides the following services as project cost consulting, tender deputizing, design management, procurement management, construction management and checking and accepting of completion, etc. Carrying out the management and controlling of the quality, safety, progress, cost, contract and information of the construction project on behalf of the employer.
(5) Arranging the checking and accepting of the project including the planning, civil works of air defense, environment protection system and fire prevention system, etc.
3 Project management plan
3.1 Project management organization structure
The project management team will carry out the management of the extended project in pre-reserved area of AMD technologies (China) Co. Ltd. on solely behalf of the company. We will carry out the employerrsquo;s directives and instructions with our manager being responsible for the project implementatio
剩余内容已隐藏,支付完成后下载完整资料
AMD技术(中国)有限公司的预定区域扩展项目的项目管理投标
1项目介绍
1.1土木工程
一种新的设备厂,约750平米,将在当前设备厂的北部进行延伸。同时应该保证货物进出成品车间的顺利运输。设备厂房的屋顶将用于冷却水塔、水箱等的放置。
其他与工程有关的土木工程。
1.2内部装饰
目前预留的3000m2区域将变成与目前工厂生产同样的装修标准的生产工厂。
新设备厂的装修标准与现有设备厂相同。
1.3暖通空调系统
生产车间的温度要求为18°C至28°C,湿度要求为35%~65%。承包商应根据这些要求和一般标准来设计空调系统的配置,以满足业主的要求。
机房和配电室的温度要求在30°C以下。
新加入的工艺排风量约为700立方米/小时。
1.4机电安装
制冷设备及附属设备将按要求安装。
空调和附属设备将根据要求安装。
工艺冷却水热转换站将按要求安装。工艺冷却水的加入量为5300kw。
将现有空气压缩系统中的管道安装到预留区域和需要压缩空气的地方。
1.5 IT系统
DDC系统
IT电缆桥架
1.6消防系统
消防系统的设计应符合国家有关规定和调整。
现有的防火系统和预留区的消防系统的控制应集成到一个集中控制系统之中。
消防系统的设计应与现行消防系统相适应。
1.7电气系统
转换站将被增大至8000kva。
电力分配将增加到电力设施之中。
技术设备的配电(具体到现场配电柜)。
照明系统。
其他相关电气系统的安装。
所有设计均应符合相关国家法规和相关行业国际通用标准的要求。
1.8所有电力设施的一般介绍
4times;2000kva空气压缩设备。
3times;450(制冷量)的冰箱。
3times;18.7m.3/hr空气压缩设备。
2times;25600m3 /小时的新风设备。
2管理公司的一般介绍
2.1公司的一般简介
建屋厂房实业发展有限公司,注册资金为3亿元(人民币),总资产近13亿元(人民币)。公司的主要业务包括:厂房相关设施的开发;车间总承包项目管理;车间工程咨询服务;车间行业管理。
2.2服务宗旨
以专业的思想提供专业的咨询、经验和管理。通过我们的专业服务,我们的雇主将获得高效率和低成本的收入并把项目风险降低到最低。
2.3提供的服务
(1)在项目决策阶段,公司参与制定项目规模和范围,提供项目规划和可行性研究报告,编制可行性研究报告。
(2)协助完成项目设计。
(3)协助发包人与承包公司、勘察公司、设计单位、供应商、监理公司签订施工合同,并按发包人的要求监督合同的执行。
(4)在项目执行阶段,我公司提供的主要服务为工程造价咨询、招标代理、设计管理、采购管理、施工管理和验收完成等。进行质量、安全、过程、成本、代表业主的建设工程合同和信息的管理和控制。
(5)安排项目的验收,包括规划、人防工程、环保系统、消防系统等。
3项目管理计划
3.1项目管理组织结构
项目管理团队仅全权代表公司,进行对AMD技术(中国)有限公司的扩展项目预留区域的管理。我们将与我们的经理一起执行雇主的指示和指示,负责项目的实施。组织结构如下:
公司
雇主
探索与设计
项目管理团队
政府的批准
招标代理
土建工程
暖通空调系统
电气安装
设备系统
安全
文件
3.2工程总进度表
(1)勘察设计:2006.1-2006.2.15
(2)在项目的早期阶段,政府批准2006.3.15
包括规划、环保、人防、防火、防雷、白蚁预防、质量监督等部门。
(3)承包商投标、监理公司和设备供应商:2006.1-2006.3
(4)放大变电站功率:2006.1-2006.3
(5)每名承建商进场施工
扩展设备厂2006.3.1-2006.5.15
预留区域的变更2006.3.1-2006.4.30
扩建设备厂装修安装
2006.4.5-2006.5.15
项目集成测试和试运行2006.5.16-2006.5.31
该项目的完成2006.5.31
3.3工程造价管理
(1)工程造价的控制将严格按照《工程造价管理程序》执行。
(2)设计阶段是成本控制最重要、最有效的阶段,包括成本估算、设计方案的审查与实施、设计标准的控制等。
(3)在投标阶段,尽量选择投标报价较低、业绩优秀、信誉良好的投标者,按合同要求和施工图要求控制造价。
(4)在施工阶段,严格按照“工程变更控制程序”控制工程变更。
(5)物料的选择应根据总成本的要求,来控制每种物料的选择。
(6)在竣工决算阶段,根据项目类别按统一的成本分解规则,列出所有的成本变化,分析项目成本控制,总结经验,保存文件为未来项目的成本计划作基础。
3.4分包工程方案管理
(1)主要分包工程包括:
1)项目设计
2)工程监理
3)地质勘探项目
4)土建工程及安装
5)装修工程
6)铝合金门窗;幕墙
7)市政工程
8)景观绿化
10)高低压配电
11)信息系统
12)供水与防火
13)各种设备的安装
(2)分包商的评估和选择
1)根据以下责任分配,管理分包商和供应商:
项目管理团队将协助业主选择和评估项目的规划与设计分包商,该项目的地质勘探工作,并负责分包商的协调:项目监理、土建、安装、铝合金门窗、幕墙、消防、市政工程、园林绿化、高低压配电、IT系统、装饰装修、设备安装等。
- 我们将以书面的形式提供分包商和供应商的资质要求,并根据规定的要求确认潜在分包商的资质。
(3)分包商的管理和沟通
1)项目管理团队将按照《施工质量管理》、《工程总监理计划》、《材料设备质量控制》和《招标投标项目成本控制》等规定管理分包商。管理方法包括:质量监督、工作进度、安全文明施工、定期沟通会议。
2)对于现场发现的问题,我们将要求分包商通过书面形式的工作关系表来改善。
3.5项目设计管理
项目设计管理的主要内容:
项目管理团队将按照以下方法管理整个项目的设计过程:
1)制定书面的监测计划,明确整个设计过程的控制要求;
2)参与设计评价,提出评价思路;
3)根据监测计划监督和检查整个设计过程;
4)评估和接受最终设计文件;
5)设计变更的检查与控制。
3.6施工质量管理
我们将负责编制“施工质量监督计划”,明确整个施工过程的重要质量控制点,明确质量控制责任和方法。根据《建筑工程质量监督计划》的要求,对整个施工过程中的控制点进行监督,并以书面形式进行记录。
3.7材料和设备的质量控制
(1)有关物料及设备将被划分为A供应和B供应。
(2)由乙方提供的物料必须向主管报告相关数据以确认,并且一些重要材料必须同时由业主确认。样品应保留。
3.8现场安全管理
项目管理团队应严格按照国家法律、法规的现场安全管理,充分发挥监理公司的职能,检查和监督分包商完善安全生产保证体系”,执行建设强制性标准,并通过各种方式如例会,巡逻,平行检验和侧支架等,确保所有的安全设施和措施是有效的。同时,项目管理团队需要监理公司和分包商每周报告安全审计报告,并且报告将被项目管理团队收集中上报业主。
3.9验收管理
(1)验收管理主要包括以下几个阶段:
1)分包工程的验收
2)检查和验收分部工程
3)规划验收
4)环境保护体系的验收
5)消防系统验收
6)竣工验收
(2)全过程验收管理将参照政府制定的标准,分包和分包工程验收主要由施工企业和监理公司执行。项目管理组参与部门和分包工程的验收,组织单位工程验收。
(3)项目管理团队将根据国家标准的要求建立书面的“验收计划”,明确业主在验收过程中应确认的项目,并按计划进行验收。
(4)项目管理小组根据《验收计划》进行验收后,向业主报告书面验收记录。
4难点分析与对策
(1)工地工作面小,安全文明施工管理困难。
合理科学地规划施工场地。大面积、大面积、大噪音的大构件的加工和制造,将在室外进行,并运至现场。同时派出人员对施工过程进行监督检查,合理安排施工方案。
(2)时间短,有很多危险因素。
建立合理的组织结构,明确可行的管理目标。采用科学的管理方法和管理措施,跟踪和检查项目时间的每个节点。合理规划风险管理目标,科学分解和分析项目风险,制定可行的方案,避免、减少、控制和转移风险。
(3)与政府职能部门及供电部门的协调是非常重要的,因为时间较短。
公司为本地企业,兼职人员为本地人。我们在苏州工业园区的多年建设过程中,与政府职能部门和供电部门,保持着良好的长期广泛的商业关系。我们在各部门有良好的信誉,与各部门建立了良好的人际关系。
(4)土木工程、安装、装修及防火方面的协调
各种工作的协调对于按时完成和使用项目是非常重要的。项目管理团队由土木工程、安装、装饰、防火等方面有丰富经验的人员组成。采用会议、访问和书面报告的方法,保证项目目标时间目标的实现。
5项目管理的报价
序号. |
成本项目名称 |
单位 |
数量 |
单价 |
总计 |
备注 |
1 |
设计费 |
m2 |
3750.0 |
95.00 |
356,250.00 |
|
2 |
地质勘探顾问费 |
项目 |
1.0 |
80,000.00 |
80,000.00 |
|
3 |
现场管理费用 |
项目 |
1.0 |
600,000.00 |
600,000.00 |
|
4 |
操作费 |
项目 |
1.0 |
180,000.00 |
180,000.00 |
|
5 |
政府收费 |
项目 |
1.0 |
120,000.00 |
120,000.00 |
|
6 |
工程估算及证明报价 |
项目 |
1.0 |
150,000.00 |
150,000.00 |
|
7 |
图纸审查费 |
项目 |
1.0 |
120,000.00 |
120,000.00 |
|
8 |
验收和文档归档 |
项目 |
1.0 |
90,000.00 |
90,000.00 |
|
9 |
工程保险费 |
项目 |
1.0 |
100,0 剩余内容已隐藏,支付完成后下载完整资料 资料编号:[482502],资料为PDF文档或Word文档,PDF文档可免费转换为Word |